Overall Plant Summary
Shift A · 06:00 - 14:00 · 7 running, 2 warning, 1 stopped
Total Machines
10Looms
7 of 10 in production
Avg. Efficiency
93%
Plant weighted average
Average RPM
200rpm
Across looms in motion
Run / Operating Time
10Hrs
Average per loom this shift
Fill Stop (Weft Stop)
10 Times / 17m
Plant total 100 Times / 170 Mins
Pile Warp (P)
22 Times / 18m
Plant total 220 Times / 180 Mins
Ground Warp (G)
18 Times / 16m
Plant total 181 Times / 161 Mins
Machine Grid · Loom 001–010
Select any loom to open its full telemetry and stoppage breakdown.